Admiral Callaghan Ln. Pavement Rehabilitation

Exisitng potholes on Adm. Callahan LaneSummary:

Remove and replace existing asphalt concrete pavement. Over excavate deleterious subgrade. Install new standard handicap curb ramps. Replace striping and pavement markings. Raise utility irons to finish grade.

Cost: $898K Engineer's Estimate
$743K Construction Contract

Status: Under Construction

Schedule

  • April 2, 2013 - Advertise for bids
  • April 18, 2013 - Bid opening
  • May 28, 2013 - Award construction contract
  • June 2013 - Notice to Proceed with construction
  • July 31, 2013 to August 8, 2013 - Overnight construction work (Public Notice)

Project Documents

Go to the following location to access project files.

If you have questions contact Joshua Sanchez, Project Manager (707) 648-5229, jsanchez@ci.vallejo.ca.us.